Independent School

41% Electricity Reduction8 Month Payback

A common issue is where separate building control systems are installed but not integrated correctly or commissioned to work optimally together. This is what we found at an Independent school with a recently built building defaulting to higher than designed energy consumption. With the implementation of ecoDriver BEMS to provide interoperability and transparency of the buildings control systems, anomalies were identified and fixed resulting in significant maintainable savings.

Case Studies

Manufacturing Facility

32% Gas Reduction6 Month Payback This case study illustrates how we applied Industry 4.0 principles to design, build, implement and commission a building automation system,

Learn More

Secondary School

10% Electricity Reduction4 Month Payback Visibility of energy profile data makes identifying ‘quick win’ savings much simpler. Following a period of data capture and review,